彩钢板在工程中的施工程序一般为:抄平放线→吊点放线→安装吊筋→地槽安装→隔墙安装→吊顶板安装→圆弧铝配件安装→门窗安装→自检清理→验收。下面济南彩钢板厂为您讲讲彩钢板吊顶、隔墙、门窗施工的事项。
The general construction procedure for color steel plates in engineering is: leveling and setting out → hanging point setting out → installation of hanging bars → installation of floor ducts → installation of partition walls → installation of ceiling panels → installation of arc aluminum accessories → installation of doors and windows → self inspection and cleaning → acceptance. Next, Jinan Color Steel Plate Factory will explain to you the construction of color steel plate ceilings, partitions, doors and windows.
隔墙板安装
Installation of partition panels
佰富彩1)由于彩钢板连接是企口式,安装时由一个固定点安装起,逐块拼接,安装时要做到上下垂直水平,板与板之间的接缝严密。
1) Due to the grooved connection of the color steel plate, it is installed from a fixed point and spliced one by one. During installation, it should be vertical and horizontal from top to bottom, and the joints between the plates should be tight.
佰富彩2)隔墙板安装时按照二次设计排版图预留门窗洞。
2) When installing partition panels, reserve door and window openings according to the secondary design layout.
佰富彩3)因为隔墙内管线多为电气插座,仪表配管,在安装时一定要多与电气仪表协调配合好。4)隔墙安装形成后必须做到牢固、垂直、平整彩钢板隔墙之间缝隙大小必须一致,保证整体严密性和外观性。
3) Because the pipelines inside the partition walls are mostly electrical sockets and instrument piping, it is necessary to coordinate and cooperate with the electrical instrument profession during installation. 4) After the partition wall is installed and formed, it must be firm, vertical, and flat. The gap size between the colored steel plate partition walls must be consistent to ensure overall tightness and appearance.
吊顶板安装
Installation of suspended ceiling panels
1)根据二次设计吊顶板排版布置图,吊顶板从固定一个方向开始安装,从块板起要测好它的对角度及吊顶板的水平度,之后每一块逐块拼接。两板之间企口一定要接触紧密,板缝一致。
1) According to the layout plan of the secondary design ceiling board, the ceiling board should be installed from a fixed direction. The angle and levelness of the ceiling board should be measured from the first board, and then each piece should be spliced one by one. The grooves between the two boards must be in close contact and the seams of the boards must be consistent.
2)吊顶板施工时必须做到上一块板固定牢固后才能进行下一块的安装,吊顶板下面在安装时用平木板顶撑顶位,以防损坏顶板。
2) During the construction of suspended ceiling panels, it is necessary to ensure that the previous panel is firmly fixed before proceeding with the installation of the next one. Flat wooden boards are used to support the top position of the suspended ceiling panel during installation to prevent damage to the top plate.
3)吊顶板面用专用钢梁固定,钢梁另一端用花兰调节螺丝与吊筋连接。对于大跨度的车间,两块彩钢板之间连接必须用专用“T”形铝连接。
3) The ceiling panel surface is fixed with a dedicated steel beam, and the other end of the steel beam is connected to the hanging reinforcement with a floral adjustment screw. For large-span workshops, the connection between two colored steel plates must be made using a dedicated "T" shaped aluminum connection.
4)吊顶板及吊筋等配件安装完,调整其水平度,保证吊顶平整无明显的高低不平现象发生,同时保证吊顶板的整体强度,能上人。
佰富彩4) After the installation of ceiling panels and hanging bars and other accessories, adjust their levelness to ensure that the ceiling is flat and free from obvious unevenness. At the same time, ensure the overall strength of the ceiling panel and can accommodate people.
门窗安装
Door and window installation
佰富彩1)彩钢门:不锈钢门门框在加工时必须保证焊接平整,焊后抛光好,立门框做到横平竖直,保证整樘门外观美观;门扇与门框之间加密封条,门扇与地面的之间加扫地条以保证整个门的密封程度。
佰富彩1) Color steel door: The stainless steel door frame must be welded flat during processing, polished well after welding, and the upright door frame must be horizontal and vertical to ensure the appearance of the entire door is beautiful; Add a sealing strip between the door leaf and the door frame, and add a sweeping strip between the door leaf and the ground to ensure the sealing degree of the entire door.
2)固定窗安装:固定窗中空玻璃安装时,必须保证两块玻璃中间擦拭干净无污点,然后加密封条以保证其气密性。另外,务必保护好不锈钢的外装饰面,避免划伤影响美观。
佰富彩2) Fixed window installation: When installing the hollow glass of the fixed window, it is necessary to ensure that the middle of the two glass pieces is wiped clean and free of stains, and then add sealing strips to ensure their airtightness. In addition, it is important to protect the exterior finish of stainless steel to avoid scratches that may affect its aesthetics.
3)传递窗安装:传递窗是用在两个不同洁净室环境的物品互相转换的中转站,防止不同洁净等级区域气流窜拢,保证各自区域气压分布状态稳定。净化车间传递窗,采用自动电子锁定型不锈钢传递窗,具有窗一窗自动联锁,开窗声光提醒功能,确保了不同区域的切实隔离。传递窗的安装须做到牢固、严密和美观。
佰富彩3) Installation of transfer window: Transfer window is a transfer station used for exchanging items in two different clean room environments, preventing airflow from converging in areas with different cleanliness levels, and ensuring stable pressure distribution in each area. The transmission window of the purification workshop adopts an automatic electronic locking type stainless steel transmission window, which has the function of automatic interlocking between windows and sound and light reminders when opening windows, ensuring effective isolation of different areas. The installation of the transfer window must be firm, tight, and aesthetically pleasing.
主要工序完成以后,要对彩板接缝进行打胶处理,打胶前,先将彩板之间的缝隙清理干净,以免缝道内有灰浆使胶与彩钢板之间的粘接力不强。打胶质量应做到表面均匀一致,不允许出现漏打和气孔现象。更多相关事项就来我们网站http://0082tv.com咨询!
佰富彩After the main process is completed, the joints of the color plate should be treated with glue. Before applying glue, the gaps between the color plates should be cleaned to avoid mortar in the seam, which may cause weak adhesion between the glue and the color steel plate. The quality of gluing should be uniform and consistent on the surface, and there should be no leakage or porosity. For more related matters, come to our website http://0082tv.com consulting service